Materials and bill of quantities

Does the project have the correct amount of materials?

Rainwater harvesting tank — École primaire Tujenge ·

Reported during the monitoring visit of 28 February 2026.

Fixed

Resolved through Advocacy

Status Fixed
0 daysSince the report
MediumSeverity
CategoryMaterials and bill of quantities

History

  1. Fixed

    · Monitor

    The missing quantities were delivered and checked with the management committee.

  2. Reported

    · Monitor

  3. Proof of fix

    · Anonymous citizen

    Fix observed during the monitoring visit of 31 May 2026.

  4. Verified (upcoming step)

How the problem was fixed

The missing quantities were delivered and checked with the management committee.

Case study

Insufficient quantity of materials: problem fixed at École primaire Tujenge thanks to citizen monitoring

The Integrity Club reported on EduCheck: insufficient quantity of materials. The problem was published and sent to the project management committee and the contractor.

Read the case study