Construction quality
Is the project using materials of the correct type and quality?
Rehabilitation of a school building — Institut technique Le Progrès ·
Reported during the monitoring visit of 12 January 2026.
Resolved through Advocacy
History
-
Fixed
The faulty materials were removed and replaced by materials matching the bill of quantities.
-
Reported
-
Progress
Problem still observed on 13 February 2026.
-
Proof of fix
Fix observed during the monitoring visit of 14 May 2026.
-
Verified (upcoming step)
How the problem was fixed
The faulty materials were removed and replaced by materials matching the bill of quantities.
Case study
Poor quality materials: problem fixed at Institut technique Le Progrès thanks to citizen monitoring
The Integrity Club reported on EduCheck: poor quality materials. The problem was published and sent to the project management committee and the contractor.