Materials and bill of quantities
Have you received a full and accurate copy of the bill of quantities for this project?
Rehabilitation of a school building — École primaire Espoir ·
Reported during the monitoring visit of 13 December 2025.
Verified
Resolved through Advocacy
Status
Verified
0 daysSince the report
MediumSeverity
CategoryMaterials and bill of quantities
History
-
Fixed
-
Verified
-
Reported
-
Proof of fix
Fix observed during the monitoring visit of 16 January 2026.
How the problem was fixed
A copy of the bill of quantities was handed to the Club and posted at the school.
Case study
Bill of quantities not shared: problem resolved at École primaire Espoir thanks to citizen monitoring
The Integrity Club reported on EduCheck: bill of quantities not shared. The problem was published and sent to the project management committee and the contractor.