Construction quality

Is all construction work being performed to the correct standard? For example, are foundations or toilet pits being dug to the correct depth?

Construction of 3 classrooms — École primaire Lumière ·

Reported during the monitoring visit of 3 January 2026.

Fixed

Resolved through Advocacy

Status Fixed
0 daysSince the report
MediumSeverity
CategoryConstruction quality

History

  1. Fixed

    · Monitor

    The substandard works were redone under an engineer’s supervision.

  2. Reported

    · Monitor

  3. Proof of fix

    · Anonymous citizen

    Fix observed during the monitoring visit of 13 February 2026.

  4. Verified (upcoming step)

How the problem was fixed

The substandard works were redone under an engineer’s supervision.

Case study

Works not built to standard: problem fixed at École primaire Lumière thanks to citizen monitoring

The Integrity Club reported on EduCheck: works not built to standard. The problem was published and sent to the project management committee and the contractor.

Read the case study