Construction quality
Is the project using materials of the correct type and quality?
Construction of 3 classrooms — École primaire Lumière ·
Reported during the monitoring visit of 3 January 2026.
Reopened
Status
Reopened
0 daysSince the report
MediumSeverity
CategoryConstruction quality
History
-
Reopened
-
Fixed
-
Reported
-
Progress
Problem still observed on 13 February 2026.
-
Proof of fix
Fix observed during the monitoring visit of 17 April 2026.
-
Acknowledged (upcoming step)
-
Fixed (upcoming step)
-